Transformer Cooling Modifications
Army Corps. of Engineers, Detroit Dam, Oregon
Service Provided
- Removal of six existing transformer heat exchangers, associated piping, and supports
- Fabrication and installation of new structural steel supports
- Installation of six new transformer heat exchangers
- Installation of new 2-1/2" copper oil supply and return piping (60 LF)
- Installation of 3" galvanized threaded cooling water supply and return piping (140 LF)
- Pressure test, oil flushing, and commissioning of new system.
- Installation of new nitrogen blanket system, including 400LF of 3/8" SS tubing.
- Project management and coordination
Project Statistics
- On schedule and under budget
- Trouble-free startup
Project Timeline
- Start date: December 2008
- Completion date: February 2009
Greenberry Industrial is a full service industrial general contractor and fabricator serving clients from our facilities in Corvallis and Portland, OR, Burlington, WA, and Ontario, CA. We manage or provide all structural, civil, and mechanical disciplines in industrial construction including boiler making, civil and concrete, heavy rigging, millwright and equipment setting, pipe spooling, and steel erection.